Step By Step Procedure to Install Kitchen Ota Properly
- Detailed drawing should be available.
- The position & marking of vertical & horizontal supports should be marked on wall as per drawing
- All chiseling work for vertical & horizontal supports should be complete before plastering.
- The chiseling for sufficient bearing should be done by cutter machine only
- The vertical support should be in line & plumb
- Fixing of sub base of platform on the vertical support should be in line & level
- Ensure that the nahani trap should be fixed at sink bottom & sealing of the hole of outlet in wall with rich cement mortar
- Ensure that proportion of mortar should be 1:6
- Height of platform should be as per drawing from FFL.
- Facia should be as per details shown in drawing & should be anchored with clits (washer).
- A slot should be left for gas pipe line in kitchen platform.
- Hole should be drilled in platform for inlet & outlet pipes.
- All joints should be filled with joint filler
- All edges of the top should be rounded off & polished
- Top of platform should be covered with POP
- Cleaning should be done properly
- Curing should be done for min 3 days